Our Projects

Sewer Call Off Maintenance Phase 1

Project Title

Sewer Call Off Maintenance Phase 1

Project ID

AA-DOM/13-14/M/1542-4.07/G

Project Brief

The scope of the project is to upgrade the sewer pipeline within the following catchment areas in Doha.

PS 1 (Zone 1) PS 5 & 31 (Zone 13) PS 6 (Zone 15) PS 7 (Zone 27) PS 10 (Zone 25) PS 11 (Zone 25)

The scope of works mainly is for the following:

  • Replacement/repair of gravity sewer lines/house connection including also construction of new pipelines and chambers
  • Re-construction of manholes including also new manholes.
  • Refurbishment of manholes
  • Reinstatement work.

Commencement Date

05 January 2014

Client Public Works Authority (Ashghal)
Year completed: 2016-10-31
Project status: completed
Price: QR 71,460,409.00